Friday, November 29, 2019 Making Progress Newsletters Since the Site C Clean Energy Project began construction four years ago, a lot of progress has been made—and much of the work has been done by Local 68 members. Here are some notable achievements so far: Left bank slope stabilized 11 million cubic metres of earth moved 2 river tunnels excavated with a smooth concrete lining installed Concrete foundation for the powerhouse on the right bank completed, with powerhouse construction well underway Substation 70% complete 50 transmission towers raised Updates to Peace Canyon substation completed—first Site C asset in service Portions of Highway 29 realigned between Fort St. John and Hudson’s Hope 4,300 workers on site On track to meet river diversion in September 2020 On track to meet final in-service date of 2024 Source: Peace River Hydro Partners You might be interested in Standing Your Ground, and Staying Steady on the Job 4 Jun 2026 CLAC Partners with Alberta Government to Advance Skilled Trades Training and Accelerate Certification 4 Jun 2026 Strathcona Mechanical Workers Ratify New Agreement Providing Wage, Scheduling Improvements 3 Jun 2026 Ready to Deliver 3 Jun 2026