Friday, November 29, 2019 Making Progress Newsletters Since the Site C Clean Energy Project began construction four years ago, a lot of progress has been made—and much of the work has been done by Local 68 members. Here are some notable achievements so far: Left bank slope stabilized 11 million cubic metres of earth moved 2 river tunnels excavated with a smooth concrete lining installed Concrete foundation for the powerhouse on the right bank completed, with powerhouse construction well underway Substation 70% complete 50 transmission towers raised Updates to Peace Canyon substation completed—first Site C asset in service Portions of Highway 29 realigned between Fort St. John and Hudson’s Hope 4,300 workers on site On track to meet river diversion in September 2020 On track to meet final in-service date of 2024 Source: Peace River Hydro Partners You might be interested in #WomenWednesday - Shandora Threadgould 22 Jul 2026 The Power of Asking for Help 20 Jul 2026 How to Manage an Insecure Leader 16 Jul 2026 Heat of the Moment 13 Jul 2026